Obetsebi Lamptey to Pamprom road to reopen to traffic mid-December – GARID

The road from the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction is expected to reopen to motorists between December 15 and 20, 2026, after 90 per cent of Phase One of a…

Published 3 min read

Obetsebi Lamptey to Pamprom road to reopen to traffic mid-December – GARID

The road from the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction is expected to reopen to motorists between December 15 and 20, 2026, after 90 per cent of Phase One of a major drainage project was completed, the Greater Accra Resilient and Integrated Development (GARID) Project has said.

GARID Project Manager Cephas Ofori told Channel One News that only backfilling and restoration of the road pavement remain. Contractors are targeting the mid-December deadline to ease congestion around the interchange during the Christmas season.

"We are targeting around the 15th to 20th of December. That is when we are opening the road to the motoring public, from Obetsebi Lamptey through to the Metro Mass area, which we call the Pamprom Crossing," he said.

Mr Ofori said the major construction activities, including demolition, excavation, construction of base walls and installation of cover slabs, have been completed. Work on Phase Two, which runs from the Pamprom Crossing to First Light, has begun.

Traffic management

GARID Communications Specialist Philip Dunyo said public education and the provision of alternative routes helped manage traffic around the construction area. He said motorists largely complied with the arrangements introduced before and after the closure, which helped prevent major gridlock and kept traffic moving.

Background

The westbound carriageway of the Dr Busia Highway from Pamprom Junction was closed to vehicular traffic on Monday, September 7, 2026, to allow construction of an underground drain in the Kaneshie enclave. The closure initially caused heavy congestion: commuters were stranded for hours as vehicles were diverted onto already congested routes.

The project is building a double-cell underground rectangular stormwater drain from Pamprom Junction to First Light Junction. The drain will be 10 metres wide and cover a 1.5-kilometre stretch, and will replace an existing system of two pipes, each 1.2 metres in diameter. It will also link the recently completed drainage section at the Accra Academy campus to the existing drain at Pamprom Junction.

Project Coordinator Dr Kwadwo Ohene Sarfo said the work would be carried out in phases because of its scale and location. The first phase had been scheduled to continue till the end of November 2026, and Pamprom Junction was initially expected to reopen in the first week of December, so the new window is a few days to two weeks later than first announced.

Not all of the closed corridor will reopen. The westbound section from Kaneshie Station to First Light Junction will remain closed until August 2027 to allow the underground drains to be completed.

Flood control in the Odaw Basin

GARID aims to reduce flood risks, improve solid waste management and upgrade basic infrastructure in flood-prone, low-income communities within the Odaw River basin. The Kaneshie works form part of government's wider flood mitigation efforts. Works, Housing and Water Resources Minister Ahmed Ibrahim has directed the contractor to implement comprehensive traffic management measures during the closures.