Government shifts Tema–Akosombo road project to Big Push as construction gathers pace

Construction works on the 64-kilometre Tema–Akosombo stretch of the Eastern Corridor Road (N2) are expected to gain fresh momentum following the government’s decision to secure alternative funding…

Published 6 min read

Government shifts Tema–Akosombo road project to Big Push as construction gathers pace

Construction works on the 64-kilometre Tema–Akosombo stretch of the Eastern Corridor Road (N2) are expected to gain fresh momentum following the government’s decision to secure alternative funding arrangements to accelerate the long-delayed project.

The project, being executed by German construction company INZAG GmbH, is a major component of Ghana’s road infrastructure development programme and is expected to improve connectivity between the Port of Tema, the Eastern Region and communities along the Eastern Corridor.

The latest development follows a decision by the government to migrate the project onto its flagship Big Push infrastructure programme, replacing the previous loan-dependent financing arrangement with funding from domestic resources.

The Minister of Roads and Highways, Kwame Governs Agbodza, announced the decision during an inspection of ongoing construction works on November 10, 2026.

He explained that the change would affect only the source of financing and would not require the government to terminate or renegotiate the existing contract with INZAG.

According to him, the government has the capacity to finance the remaining works locally, allowing the contractor to continue without the delays associated with accessing the original external credit facility.

The minister said the arrangement formed part of a broader government policy to move selected strategic road projects away from delayed loan financing and provide alternative funding to ensure their timely completion.

A revised construction programme submitted by the contractor is targeting completion around October 2028, subject to the availability of resources and sustained progress on site.

Mr Agbodza stressed that the contractor must demonstrate visible progress along the entire stretch rather than concentrate construction activities around selected sections.

A strategic link for trade and transportation

The Tema–Akosombo road forms part of the approximately 700-kilometre Eastern Corridor, one of Ghana’s important north–south transport routes connecting the coastal areas to the northern parts of the country and neighbouring landlocked countries, including Burkina Faso.

The wider corridor begins around the Tema Motorway Roundabout and extends through the Volta and Oti regions towards the Upper East Region and the Burkina Faso border.

The road is particularly important because it provides an alternative transportation route for the movement of goods and passengers between southern Ghana and the northern parts of the country.

When completed, the upgraded Tema–Akosombo section is expected to reduce travel times, improve road safety, lower vehicle operating costs and facilitate the movement of agricultural produce, industrial goods and other commodities.

It will also strengthen the connection between the Port of Tema and inland markets, improving Ghana’s potential as a regional logistics and distribution hub.

The project involves upgrading the existing road into a modern highway, with a dual carriageway and service roads on sections between Ashaiman and Kpong, alongside a single carriageway section towards Atimpoku.

Other components include a flyover at the Ashaiman Roundabout, an interchange at Asutsuare Junction, three river bridges, 11 pedestrian footbridges, drainage systems, street lighting and pedestrian walkways.

These facilities are expected to improve traffic flow, enhance safety and reduce the difficulties motorists and residents currently encounter along the route.

The 64-kilometre project, also described as the Ashaiman Roundabout–Akosombo Junction road, has an estimated contract value of approximately €256 million.

Financing challenges and construction delays

Construction commenced in May 2022 but experienced significant delays following Ghana’s economic and debt difficulties, which affected the availability of financing for several major infrastructure projects.

The project was initially supported by an export credit facility arranged through Standard Chartered, with German export credit support from Euler Hermes.

However, the country’s debt restructuring process and difficulties accessing the financing contributed to a prolonged slowdown in construction.

In February 2026, German Ambassador to Ghana, Frederik Landshöft, visited the project site near Afienya and expressed optimism about the resumption of full construction activities following the November 2025 bilateral debt restructuring agreement between Ghana and Germany.

At the time, he indicated that the contractor’s workforce, which stood at approximately 450, could increase to about 900 workers, potentially tripling the pace of construction.

He also commended the engineering standards, quality assurance systems and safety measures being implemented by INZAG.

An interesting feature of the project is its commitment to women’s participation in the construction industry, with approximately one-third of the workforce reportedly comprising women working as welders, heavy machinery operators and in supervisory and leadership positions.

The development highlights the potential of major infrastructure investments to create employment opportunities and promote skills development beyond the traditional construction workforce. Ghanaian Times +2

Government steps up supervision

During his November 10 inspection, Mr Agbodza also directed contractors working on the Eastern Corridor to strengthen their operational capacity and improve traffic management to minimise inconvenience to motorists, particularly during the Christmas festivities.

The directive affected INZAG and other contractors undertaking sections of the Ashaiman–Atimpoku and Ashaiman–Afienya road projects.

The minister stressed that construction activities must not result in prolonged traffic congestion and called for additional equipment, personnel and effective coordination among contractors.

He also urged contractors to ensure that motorists could continue using the affected roads safely while construction works progressed. CitiNewsroom.com +1

The government’s funding decision is expected to provide greater certainty for the project, although its success will depend on the timely release of funds, effective supervision and the contractor’s ability to maintain the revised construction schedule.

Eastern Corridor remains a national priority

The Tema–Akosombo project is part of a wider effort to improve the Eastern Corridor, which is considered essential to Ghana’s domestic transportation network and regional trade ambitions.

President John Dramani Mahama, speaking at the 2026 Hogbetsotso Festival in the Volta Region on November 8, announced that most sections of the Eastern Corridor Road were expected to be completed by the end of 2027.

He also disclosed plans to commence construction of the Volivo Bridge over the Southern Volta River in the first quarter of 2027.

The proposed bridge is expected to provide an important additional connection between the southern and northern sections of the country and improve transportation along the corridor. Information Services Department

Meanwhile, the government has been pursuing improvements to other sections of the route, including the Have–Hohoe stretch, where the Roads and Highways Minister recently expressed dissatisfaction with the contractor’s pace of work.

The broader programme underscores the government’s intention to improve connectivity, reduce transportation costs and open up economic opportunities in communities along the corridor.

For businesses, farmers, transport operators and traders, the completion of the Tema–Akosombo road could significantly improve the movement of goods between production centres, markets and the country’s principal seaport.

It could also stimulate investment in logistics, warehousing, manufacturing, agriculture and commercial activities along the route.

Ultimately, the success of the project will be measured not only by the completion of the physical infrastructure but also by its impact on transportation efficiency, employment, regional trade and economic growth.

With the government switching to domestic financing and INZAG expected to work under a revised completion programme targeting October 2028, attention will now turn to whether the renewed funding arrangement can deliver the long-awaited road within the revised timeframe.

Editorial note: The October 2028 target relates to the Tema–Akosombo Lot 1 project. President Mahama’s end-of-2027 announcement concerns most sections of the wider Eastern Corridor and should not be interpreted as a replacement completion date for this particular 64-kilometre project.