Six Accra Flood Defences Stuck at Contract Stage as Finance Ministry Holds Back Clearance
Six flood-control projects designed to shield Accra from the kind of devastation that killed at least 12 people in June are stalled at the contract-award stage, with the Works Ministry unable to…
بقلم Ralph Waldo Emerson
صحفي
نُشر في مدة القراءة: 4 د

Six flood-control projects designed to shield Accra from the kind of devastation that killed at least 12 people in June are stalled at the contract-award stage, with the Works Ministry unable to begin construction until the Finance Ministry grants financial commitment authorisation.
Works, Housing and Water Resources Minister Ahmed Ibrahim told Parliament on Wednesday, November 18, that the six schemes under the World Bank-funded Greater Accra Resilient and Integrated Development (GARID) project are “at the tendering and contract award stage,” but cannot proceed without the Finance Ministry’s sign-off. The projects are: reconstruction of the Abossey Okai Bridge; construction of the Atomic East and West detention ponds; improvement works on the Alajo drain; repackaged works on the Nima drain; and installation of the Accra Flood Early Warning Systems.
The Nima-Paloma Wreckage
The most politically charged item is the Nima-Paloma drainage project, a 1.5-kilometre box culvert intended to carry stormwater from Nima-Paloma to the Odaw River. The contract was terminated in July 2026 for poor performance, after the contractor had completed just 13 per cent of excavation works, 25 per cent of demolition of the existing drain, 9.7 per cent of concrete base casting and 9.5 per cent of wall casting. The project had commenced in July 2024 with an 18-month duration.
Ibrahim said the ministry is engaging the World Bank on the “most appropriate procurement arrangement” for a new contractor, and that Dredge Masters has been hired to desilt the drain in the interim to keep stormwater flowing. Additional local measures have been put in place to reduce flood exposure for communities upstream and downstream of the unfinished works.
The Finance Ministry Bottleneck
The delay is not new. A World Bank implementation update released in May 2026 found that GARID’s implementation had been “significantly constrained by fiscal measures introduced by the Ministry of Finance during 2025,” including a ceiling on project disbursements and the temporary sweeping of GH¢13.8 million from the project’s designated account. The measures left unpaid Interim Payment Certificates, delayed contractor payments and slowed civil works, even as the project had access to its full $350 million financing.
As of April 14, 2026, only $137 million—about 40 per cent of total project financing—had been disbursed, with virtually no disbursements between November 2024 and March 2026. The Project Coordination Unit estimated a $40.8 million funding requirement for 2026, but the Finance Ministry allocated only about $17.5 million, leaving a substantial shortfall. A request for commitment authorisation covering $79.8 million in civil works contracts, submitted by the Works Ministry, was still awaiting approval as of the World Bank’s report.
June 29: The Flood That Exposed the Gap
The urgency is acute. On June 29, 2026, heavy rains—estimated at about 140 millimetres—submerged swathes of Accra, displacing thousands, destroying property and claiming at least 12 lives, including electrocution deaths in Alajo. The floods reignited a political row over GARID’s delays. The World Bank noted that although the project’s flood early warning system was fully operational, no public warning was issued ahead of the disaster. The GARID coordinator, Dr Ohene Sarfoh, has blamed political interference for undermining the project’s effectiveness.
The Money and the Mandate
GARID was approved at $350 million to address flooding in the Odaw Basin, with an additional $150 million in financing approved in 2023, extending the project’s closing date to 2027. The project combines drainage works with solid-waste management and community upgrading. Parliament has since approved a further $150 million World Bank loan, though the minority raised accountability questions about earlier spending during a disputed vote.
The Minister said GARID is pursuing both structural and non-structural measures across the Odaw Basin, including dredging the Odaw River—targeted for completion by December 2027—and addressing infrastructure bottlenecks such as bridges that restrict water flow.
Until the Finance Ministry signs the commitment authorisation, however, the six new defences remain on paper. For communities along the Odaw and its tributaries, the next heavy rain will test whether Accra’s flood infrastructure is ready—or still waiting.